Navigator > Tasks > Accounts Payable > Enter Shipments > Additional Costs tab
Enter additional costs to be apportioned as additional cost for the shipment lines based on the Type selected. The Receipt cost for shipment lines includes the unit additional cost. The unit additional cost is also saved to the Supplier record for the product.
Note: If Additional Costs are changed after Invoices and Receipts have been posted, you will need to click
Update Costs (Alt+T) to save the changes.
Creditor Code |
The Creditor code for the Additional Cost. This is the creditor who invoiced you, for example, it could be a freight company. |
|
Cost Code |
The type of Cost. Defaults from the Creditor. |
|
Description |
The Cost code description, can be edited. |
|
Period |
The period in which the costs were incurred. |
|
Date |
The date the costs were incurred. |
|
Reference |
The creditor's invoice reference for the cost. |
|
Amount |
The amount to be apportioned. |
|
Type |
Additional costs can be apportioned to products on a shipment, for example, by Weight, by Volume. Default is Manual if Manually Apportioned is selected from the Receipt tab. Additional Cost Apportionments are calculated as follows, Weight ApportionWeightAmountBs = Sum(AdditionalCost.CostAmountBs where AdditionalCost.ApportionType = Weight) ApportionTotalWeight = Sum(ShipmentLine.ExtendedWeight where ShipmentLine.ManuallyApportion = False) Then for each ShipmentLine where ShipmentLine.ManuallyApportion = False and ShipmentLine.ExtendedWeight <> 0 additional cost per unit from weight = ApportionWeightAmountBs * (ShipmentLine.ExtendedWeight / ApportionTotalWeight) / ShipmentLine.Quantity Volume Apportion Volume AmountBs = Sum(AdditionalCost.CostAmountBs where AdditionalCost.ApportionType = Volume ) ApportionTotal Volume = Sum(ShipmentLine.Extended Volume where ShipmentLine.ManuallyApportion = False) Then for each ShipmentLine where ShipmentLine.ManuallyApportion = False and ShipmentLine.Extended Volume <> 0 additional cost per unit from Volume = Apportion Volume AmountBs * (ShipmentLine.Extended Volume / ApportionTotal Volume ) / ShipmentLine.Quantity Cost Apportion Cost AmountBs = Sum(AdditionalCost.CostAmountBs where AdditionalCost.ApportionType = Cost) ApportionTotal Cost = Sum(ShipmentLine.Extended Cost where ShipmentLine.ManuallyApportion = False) Then for each ShipmentLine where ShipmentLine.ManuallyApportion = False and ShipmentLine.Extended Cost <> 0 additional cost per unit from Cost = Apportion Cost AmountBs * (ShipmentLine.Extended Cost / ApportionTotal Cost ) / ShipmentLine.Quantity Quantity Apportion Quantity AmountBs = Sum(AdditionalCost.CostAmountBs where AdditionalCost.ApportionType = Quantity) ApportionTotal Quantity = Sum(ShipmentLine.Extended Quantity where ShipmentLine.ManuallyApportion = False) Then for each ShipmentLine where ShipmentLine.ManuallyApportion = False and ShipmentLine.Extended Quantity <> 0 additional cost per unit from Quantity = Apportion Quantity AmountBs * (ShipmentLine.Extended Quantity / ApportionTotal Quantity) / ShipmentLine.Quantity |
|
Currency |
The currency of the amount. |
|
Amount Bs |
The amount converted to base currency at the exchange rate. |
|
Rate Type |
The Rate Type for the exchange rate. |
|
Exchange Rate |
The exchange rate to be applied to the cost. If the Shipment Line field is selected (see Customise below), the Exchange Rate and Creditor Code of the Shipment are used. |
|
Grid toolbar |
||
|
Expand Toolbar |
Expand the toolbar to give access to all toolbar options. Press |
|
Insert |
Insert a new line. |
|
Move |
Move selected lines. |
|
Delete |
Delete a selected line. |
|
Customise |
Opens Customise Fields, you can customise the fields visible in the grid. |
|
Insert invoice for cost |
Inserts an Invoice Transaction for the Additional Cost line, for the Creditor. Opens AP Transactions. If an invoice has already been created using the Reference, a warning will be displayed. |